Blog to follow the renovations of the Anna Curtis Youth Center of Powell House, the retreat and conference center of New York Yearly Meeting.
The renovation will make the ACC healthier, green and ACCessible!
Saturday, June 14, 2008
pouring cement for foundation wall and abatement
Friday, the foundation wall was poured. They had quite a time getting the concrete to pass through the long hose from the cement mixer. Hammers and sledgehammers were used in this process. This view clearly shows the new sunporch area.
At the same time, the asbestos company were painting the floor of room 1 in ACC to finish the abatement. This was after the final air quality test. The ACC passed with flying colors!
No comments:
Post a Comment