This is the "before" photo. I'm standing in old room #3 which was at the corner upstairs and had a door leading outside to the roof. The room had to be dis-assembled including the roof! We're looking north towards Pitt Hall.
So Thursday night before the work weekend began, Liseli, Buffy and Aldona Januszkiewicz began. CNS had put yellow marks on what needed to come down. We're looking towards the new 2nd floor Bugg House (west).
Liseli is having way too much fun! Notice the yellow marking.
Saturday morning, a crew of 6 or so began removing the shingles from the old roof over room 3. Here's Mike. Notice CNS's new roof over the old. (see other posts for the outside views)
Photo by Andy Heimer
Of course, what Mike, Andy Heimer and Neil Murdock knocked or scraped down had to be picked up and thrown into the dumpster. Here's Bing Rao picking up the pieces of the shingles and roof decking. Chris and Faith also helped with this.
minus the shingles and decking -- rafters are next.
No comments:
Post a Comment